The University of Alabama, Division of Finance and Operations

Change Order Policy for Construction Projects

Unit:  Procurement Services
Contact: Dan Rodgers
Title:  Director, Contract Administration
Effective Date: 7/1/2011
Revision Date: 03/01/2019


 
 

Purpose

The purpose of this policy is to provide a clear and concise process for implementing contract change orders for all construction projects administered through Finance and Operations.

Policy

No actual work will begin and no funds shall be expended until the Change Order Request Approval Form (CORAF) has been approved by the appropriate parties as defined in the Change Order Procedures for Construction Projects. All executed CORAFs should be incorporated into a change order within 30 days of the completion of the work described in the CORAF in order to allow the Contractor and any subcontractors to bill for work performed.

Scope

These procedures apply to all Contractors, Architects/Engineers/Consultants, and UA Personnel.

 
 

Office of the Vice President of Finance and Operations

Approved by Cheryl Mowdy, Assistant Vice President for Finance and Operations, 03/01/2019